Hotel Mélia, La Défense, France
Project data
Location: Paris, France
New construction of a hotel with 5 basement levels and 20 upper storeys
Total height: 87 m
Construction time: January 2013 to the end of 2014
Architect: Claude Vasconi
Requirements
Self-climbing formwork for complex geometries and a wide range of loads
- assembly support for the precast parapets
- for accommodating loads from steel formwork provided by the contractor
- circumferential climbing protection panel for complete, closed enclosure
Integration of a landing platform for the transport of materials
Customer
Bateg / CBC, Velizy - Villacoublay, France
Benefit to customer
- Crane-independent climbing solution
- Simple assembly of the precast parapets with protection provided by the enclosure
- High level of safety for site personnel as well as around the construction site
Jean-Francois Delmas
Senior Construction Manager
The Hotel Meliá itself is a real technical challenge whilst the site surroundings also provide severe restrictions. The PERI climbing formwork solution, based on the RCS system, fully meets our requirements - both in terms of safety as well as use.
PERI solution
- Project-specific solution with RCS system components
- Four different protection panel concepts, e.g. with special slab shoes or an FTF solution as assembly support for the precast parapets