Nile river barrage Naga Hammadi, Egypt
Project data
Location: Naga Hammadi, Egypt
330 m long barrage with 64 MW hydropower plant, weir plant with seven weirs and two 170 m long sluices.
Requirements
- tight construction time schedule
- simultaneous manufacturing of single components
- bulky, massive reinforced steel parts
- high pouring speeds
Customer
Bilfinger Berger, VINCI, Orascom
Benefit to customer
- short construction time
- fast climbing cycle sequence
- construction sequence without interruptions
- high material utilisation rate
- high quality standard
- high safety during all shuttering, reinforcement and pouring activities
Andreas Poller
Construction manager
The good experience we have had with the proven PERI systems in previous projects made us decide to again cooperate with PERI in this Naga Hammadi barrage project. All shuttering, reinforcement and pouring activities could be carried out from safe working platforms. This helped to achieve faster cycle sequences. Despite the given very short construction time we were able to reach a high quality standard.
PERI solution
- SKS and VARIO climbing formwork solution for main and intermediate pillars
- optimised cycle planning
- large-size moving units